Phase I
March 6th thru March 22nd

  • Center lanes closed.
  • Fifth Street closed to construct crosswalks and install irrigation.
  • No left turns until March 22, 2007.

Phase II
March 23rd thru June 31st

  • First Street to Eighth Street tree removal.
  • First Street to Morningside Court – intermittent lane closure of the Easternmost and Westernmost traffic lanes to allow construction of bulb outs, tree well pop outs and crosswalks.
  • First Street to Morningside Court - Installation of irrigation and electrical.
  • First Street to Morningside Court -Installation of Street lights.
  • First Street to Morningside Court –Landscaping.
  • First Street to Morningside Court –Sidewalk work.
  • First Street will be closed at Maclay Avenue for up to 15 days.
  • Second Street will be closed at Maclay Avenue for up to 15 days.
  • Third Street will be closed at Maclay Avenue for up to 15 days.
  • Fourth Street will be closed at Maclay Avenue for up to 15 days.
  • Morningside Court will be closed at Maclay Avenue for up to 15 days.
  • The East side of Second Street will permanently become a one way street exiting onto Maclay Avenue.
  • Morningside Court will permanently become a one way street exiting onto Maclay Avenue.

Phase III
July 1st thru October 31st
  • Morningside Court to Eighth Street - intermittent lane closure of the Easternmost and Westernmost traffic lanes to allow construction of bulb outs, tree well pop outs and crosswalks.
  • Morningside Court to Eighth Street - Installation of irrigation and electrical
  • Morningside Court to Eighth Street -Installation of Street lights
  • Morningside Court to Eighth Street –Landscaping
  • Morningside Court to Eighth Street –Sidewalk work
  • The Northernmost and Southernmost lanes of Glenoaks Boulevard at Maclay Avenue will be closed for up to 15 days.
  • Defoe Street will be permanently closed at Maclay.
  • Dehaven Street will be permanently closed at Maclay.

Phase IV
November 1st thru November 30th
  • First Street to Eighth Street – repave Maclay Avenue
  • Complete landscaping
  • Cleanup
  • Traffic Striping and Signage
  • Completion of the Archways at Eighth Street and at Fourth Street.


For more information please call 818-898-1222 or go to the City website at www.sfcity.org

Revised as of March 14, 2007

* The City is committed to completing the project by November 2007, weather permitting.


Fase I
Marzo 6 - Marzo 22

  • Carril central cerrado
  • Calle Fifth cerrada para pavimentar banquetas e instalar irrigación.
  • No tráfico no sepermitira vueltas a la izquierda hasta el 22 de marzo de 2007.

Fase II
Marzo 22 - Junio 31

  • Remover árboles de la calle Fifth a la calle Eighth.
  • Calle First hacia la avenida Morningside Court – Carriles de tráfico occidental y oriental estrarán cerrados durante construcción de jardineria, plantación de árboles, y construcción de paso peatones.
  • Calle First a la Morningside Court - Instalación de irrigación y eléctrico
  • Calle First a la Morningside Court -Instalación de lámparas de luz en las calles
  • Calle First a la Morningside Court –Jardinería
  • Calle First a la Morningside Court –Trabajo de banquetas
  • Calle First esquina con la calle Maclay estará cerrada hasta 15 días.
  • Calle Second esquina con la calle Maclay estará cerrada hasta 15 días.
  • Calle Third esquina con la calle Maclay estará cerrada hasta 15 días.
  • Calle Fourth esquina con la calle Maclay estará cerrada hasta 15 días.
  • Morningside Court con la calle Maclay estará cerrada hasta 15 días.
  • El lado este de la calle Second permanentemente se convertirá en calle de un sentido la avenida Maclay.
  • Morningside Court permanentemente se convertirá en calle de un sentido la avenida Maclay.
Fase III
Junio 31 - Octubre 31
    • Morningside Court hacia la calle Eighth – El carril intermitente del tráfico vial con dirección del Este al Oeste estará cerrado para permitir la construcción de jardineras, plantar árboles, y agregar banquetas.
    • Morningside Court hacia la calle Eighth - Instalacion de irrigación y eléctrico.
    • Morningside Court hacia la calle Eighth - Instalación de lámparas de luz en las calles.
    • Morningside Court hacia la calle Eighth –Jardinería.
    • Morningside Court hacia la calle Eighth – trabajo de banquetas.
    • Los carriles con dirección al norte y sur de la Glenoaks en la Maclay estará cerrada hasta 15 días.
    • Calle Defoe estará permanentemente cerrada en la avenida Maclay.
    • Calle Dehaven estará permanentemente cerrada en la avenida Maclay.
Fase IV
Octubre 31 - Noviembre 30
    • Calle First hacia la calle Eighth – repavimentación de la avenida Maclay y finalizar la construcción de jardines.
      Limpieza.
    • Pintar las divisiones de carriles y agregar los letreros.
    • Finalizar construcción de los Arcos en las calles Eighth y Fourth.


Para mas información, por favor llame al 818-898-1222 ó visite nuestro sitio de Internet www.sfcity.org.

Actualizado el 14 de marzo del 2007

*La ciudad esta cometido a completar este proyecto para noviembre del 2007, si el tiempo lo permite