Phase I
March 6th thru March 22nd
- Center lanes closed.
- Fifth Street closed to construct crosswalks
and install irrigation.
- No left turns until March 22, 2007.
Phase II
March 23rd thru June 31st
-
First Street to Eighth Street tree removal.
-
First Street to Morningside Court – intermittent
lane closure of the Easternmost and Westernmost traffic lanes
to
allow construction of bulb outs, tree well pop outs and crosswalks.
-
First Street to Morningside Court - Installation
of irrigation and electrical.
-
First Street to Morningside Court
-Installation of Street lights.
-
First Street to Morningside
Court –Landscaping.
-
First Street to Morningside Court –Sidewalk
work.
-
First Street will be closed at Maclay Avenue
for up to 15 days.
-
Second Street will be closed at Maclay Avenue
for up to 15 days.
-
Third Street will be closed at Maclay
Avenue for up to 15 days.
-
Fourth Street will be closed
at Maclay Avenue for up to 15 days.
-
Morningside Court will
be closed at Maclay Avenue for up to 15 days.
-
The East
side of Second Street will permanently become a one
way street exiting
onto Maclay
Avenue.
-
Morningside Court
will permanently become a one
way street exiting
onto Maclay Avenue.
Phase III
July 1st thru October 31st
-
Morningside Court to Eighth Street - intermittent
lane closure of the Easternmost and Westernmost traffic lanes
to allow construction of bulb outs, tree well pop outs and
crosswalks.
-
Morningside Court to Eighth Street - Installation
of irrigation and electrical
-
Morningside Court to Eighth
Street -Installation of Street lights
-
Morningside Court to
Eighth Street –Landscaping
-
Morningside Court to
Eighth Street –Sidewalk work
-
The Northernmost and
Southernmost lanes of Glenoaks Boulevard at Maclay
Avenue will be closed for up to 15 days.
-
Defoe Street will
be permanently closed at Maclay.
-
Dehaven Street will be
permanently closed at Maclay.
Phase IV
November 1st thru November 30th
-
First Street to Eighth Street – repave
Maclay Avenue
-
Complete landscaping
-
Cleanup
-
Traffic Striping and Signage
-
Completion of
the Archways at Eighth Street and at Fourth Street.
For more information please call 818-898-1222 or go to the City
website at www.sfcity.org
Revised as of March 14, 2007
* The City is committed to completing the project by November
2007, weather permitting.
Fase I
Marzo 6 - Marzo 22
Fase II
Marzo 22 - Junio 31
-
Remover árboles de la calle Fifth a
la calle Eighth.
-
Calle First hacia la avenida Morningside Court – Carriles
de tráfico occidental y oriental estrarán
cerrados durante construcción de jardineria,
plantación
de árboles, y construcción de paso
peatones.
-
Calle First a la Morningside Court - Instalación
de irrigación y eléctrico
-
Calle
First a la Morningside Court -Instalación
de lámparas
de luz en las calles
-
Calle First a la Morningside
Court –Jardinería
-
Calle First
a la Morningside Court –Trabajo
de banquetas
-
Calle First esquina con la calle
Maclay estará cerrada
hasta 15 días.
-
Calle Second esquina
con la calle Maclay estará cerrada
hasta 15 días.
-
Calle Third esquina
con la calle Maclay estará cerrada
hasta 15 días.
-
Calle Fourth
esquina con la calle Maclay estará cerrada
hasta 15 días.
-
Morningside
Court con la calle Maclay estará cerrada
hasta 15 días.
-
El lado
este de la calle Second permanentemente
se convertirá en
calle de un sentido la avenida
Maclay.
-
Morningside Court permanentemente
se convertirá en
calle de un sentido la avenida
Maclay.
Fase III
Junio 31 - Octubre 31
Para mas información, por favor llame al 818-898-1222 ó visite
nuestro sitio de Internet www.sfcity.org.
Actualizado el 14 de marzo del 2007